| Step | Step name | INITIATION | Next step | Actor |
| P10 | Submit a request (deadline: 31.08.2024) |
| P40 | Project Owner |
| P40 | Check Eligibility |
| P60,P70 | Executive Secretariat |
| P60 | Send admission notice |
| P80 | Executive Secretariat |
| P70 | Send rejection notice |
| P330 | Executive Secretariat |
| P80 | Provide project information (deadline: 22.09.2024) |
| P90 | Project Owner |
| P90 | Formality check |
| P80,P100 | Executive Secretariat |
| P100 | Identify an FASP Assessor |
| P130 | Executive Secretariat and STC |
Step | Step name | STEP 1 - SAFEGUARD CRITERIA of the ASSESSMENT | Next step | Actor |
| P130 | Assess compliance with safeguard criteria |
| P140, P160 | Assessor |
| P140 | Make improvements to meet safeguard criteria |
| P150 | Project Owner |
| P150 | Reassessment of safeguard criteria |
| P330, P160 | Assessor |
Step | Step name | STEP 2 - DIRECT CRITERIA of the ASSESSMENT | Next step | Actor |
| P160 | Assess compliance with direct criteria |
| P170, P190 | Assessor |
| P170 | Make improvements to meet direct criteria |
| P180 | Project Owner |
| P180 | Reassessment of direct criteria |
| P330, P190 | Assessor |
Step | Step name | STEP 3 - INDIRECT CRITERIA of the ASSESSMENT | Next step | Actor |
| P190 | Assess compliance with indirect criteria |
| P200, P220 | Assessor |
| P200 | Make improvements to meet indirect criteria |
| P210 | Project Owner |
| P210 | Reassessment of indirect criteria |
| P330, P220 | Assessor |
| Step | Step name | STEP 4 - CROSS-CUTTING of the ASSESSMENT | Next step | Actor |
| P220 | Assess compliance with cross-cutting criteria |
| P230, P250 | Assessor |
| P230 | Make improvements to meet indirect criteria |
| P240 | Project Owner |
| P240 | Reassessment of cross-cutting criteria |
| P330,P250 | Assessor |
| Step | Step name | CONCLUSION | Next step | Actor |
| P250 | Elaborate assessment summary report (deadline: 31.10.2024) |
| P260 | Assessor |
Revise project concept note |
| Project Owner | ||
Validate revised project concept note |
| |||
| P260 | Validation of the assessment summary report by the STC |
| P270,P280 | STC |
| P270 | Improve the summary report |
| P260 | Assessor |
| P280 | Validation of the assessment summary report by Executive Secretariat |
| P260,P290 | Executive Secretariat |
| P290 | Notify Project Owner |
| P300 | Executive Secretariat |
| P | ||||
| P300 | Publish project summary |
| P310 | Executive Secretariat |
| P330 | End | Executive Secretariat |